JENSONN POWER SYSTEM

Project Case Study: Hong Kong

Reliable Backup Power for Mission Critical Data Centre Operation


香港

Project Overview

Location:
Hong Kong

Project Type:
To setup the secondary source of power for data centre

Installed Capacity:
4x 2250KW

Objective:
Provide uninterrupted protection for a tier ready facility

Initial Situation


Reliability

As part of the data centre expansion project, the facility required a dependable emergency power solution capable of supporting critical server loads, cooling systems, and network infrastructure during grid power failure. The project demanded synchronized generator operation, automatic transfer capability, and high system reliability within limited installation space. The challenges were further stacked up with a residential surrounding which required a super silence setup

Key Challenges

Uninterrupted uptime requirement

Fast emergency power response

Synchronization of multiple generators

Limited installation space

Environmental and regulatory considerations

Proposed Solution

To support the client’s uptime and resilience objectives, a high-capacity standby power system utilizing four synchronized 2.2MW generator sets was implemented. The solution provided scalable emergency power support with redundancy, intelligent load management, and seamless integration into the facility’s electrical infrastructure to protect mission-critical operations. The set up was done in out of gauge container to cater for the super silence requirements

Technical Configuration

Implementation Timeline

1.

Engineering & Planning

Load assessment and system design

2.

Equipment Supply

Delivery of genset and auxiliary system

3.

Synchronization & Integration

Integration with switchgear & control system

4.

Testing & Commissioning

Load testing, synchronisation testing, operational verification

5.

Project Completion

System handover & operational readines

Logistics & Execution

Key Highlight

Fast-track deployment under tight timeline and challenging space conditions

Results Achieved

Successful commissioning

Reliable uptime

Operational readiness

Stable power with redundancy

Ticking all environment requirements

Project Photos

Project Impact

Increased in Power Resilience
Increased Ability to maintain continuous service
Support Scalabilty for future expansion
Improved reliability for mission operation

Conclusion

The successful deployment of seven (7) synchronized 2.2MW diesel generator sets provided the data centre with a reliable and scalable standby power solution for mission-critical operations. Through careful engineering, system integration, and commissioning, the project strengthened the facility’s operational resilience and ensured dependable backup power support for long-term infrastructure reliability.

The future of power generators for generations